All of our projects
Mallard-Ridge (Air Liquide)
Operational
usa
WAGABOX® Model
-
Commissioning
March 2022
Installed capacity
375,336 MMBtu/year
Distance to pipeline
-
Landfill gas composition
CH4
-
N2
-
Site operator
Utility
Gas offtaker

McKean (Casella)
Under construction
usa
WAGABOX® Model
2000 scfm
Commissioning
June 2026
Installed capacity
375,336 MMBtu/year
Distance to pipeline
1.2 miles
Landfill gas composition
CH4
-
N2
-

Site operator
Utility
Gas offtaker

Milhac-d’Auberoche (Suez)
Operational
fr
WAGABOX® Model
375 scfm
Commissioning
November 2022
Installed capacity
85,304 MMBtu/year
Distance to pipeline
11.2 miles
Landfill gas composition
CH4
42,00%
N2
25,90%

Site operator

Utility
Gas offtaker

Miramundo (Bioreciclaje de Cadiz)
Under construction
es
WAGABOX® Model
1500 scfm
Commissioning
October 2026
Installed capacity
272,971 MMBtu/year
Distance to pipeline
5.6 miles
Landfill gas composition
CH4
-
N2
-

Site operator

Utility
Gas offtaker

Monflanquin (Valorizon et Avergies)
Operational
fr
WAGABOX® Model
250 scfm
Commissioning
January 2026
Installed capacity
40,946 MMBtu/year
Distance to pipeline
0.2 miles
Landfill gas composition
CH4
44,80%
N2
17,90%

Site operator

Utility
Gas offtaker

Montois-la-Montagne (Suez)
Operational
fr
WAGABOX® Model
250 scfm
Commissioning
January 2023
Installed capacity
85,304 MMBtu/year
Distance to pipeline
2.8 miles
Landfill gas composition
CH4
40,70%
N2
24,80%

Site operator

Utility

Gas offtaker

New Bath (Steuben County)
Operational
usa
WAGABOX® Model
1000 scfm
Commissioning
March 2024
Installed capacity
204,729 MMBtu/year
Distance to pipeline
2.8 miles
Landfill gas composition
CH4
44,20%
N2
23,30%

Site operator

Utility
Gas offtaker

Newland Park (Wicomico County)
Under construction
usa
WAGABOX® Model
1000 scfm
Commissioning
Installed capacity
211,553 MMBtu/year
Distance to pipeline
4 miles
Landfill gas composition
CH4
-
N2
-

Site operator
Utility
Gas offtaker

Ostrom (G2)
Under construction
usa
WAGABOX® Model
2000 scfm
Commissioning
Q1-2027
Installed capacity
419,693 MMBtu/year
Distance to pipeline
1 mile
Landfill gas composition
CH4
-
N2
-

Site operator
Utility
Gas offtaker

Pavie (Trigone)
Operational
fr
WAGABOX® Model
250 scfm
Commissioning
May 2018
Installed capacity
51,182 MMBtu/year
Distance to pipeline
1.9 miles
Landfill gas composition
CH4
47,50%
N2
14,20%

Site operator

Utility

Gas offtaker

Podere Rota (CSAI)
Under construction
it
WAGABOX® Model
500 scfm
Commissioning
September 2026
Installed capacity
98,952 MMBtu/year
Distance to pipeline
0.4 miles
Landfill gas composition
CH4
-
N2
-

Site operator
Utility
Gas offtaker

Polo Industriale Scapigliato (Scapigliato)
Under construction
it
WAGABOX® Model
1500 scfm
Commissioning
December 2026
Installed capacity
313,917 MMBtu/year
Distance to pipeline
1.4 miles
Landfill gas composition
CH4
-
N2
-

Site operator
Utility
Gas offtaker

Rockingham (Rockingham County)
Under construction
usa
WAGABOX® Model
1000 scfm
Commissioning
October 2025
Installed capacity
204,729 MMBtu/year
Distance to pipeline
2 miles
Landfill gas composition
CH4
-
N2
-

Site operator
Utility
Gas offtaker

Saint-Etienne-des-Grès (Enercycle)
Operational
ca
WAGABOX® Model
2000 scfm
Commissioning
May 2023
Installed capacity
443,578 MMBtu/year
Distance to pipeline
-
Landfill gas composition
CH4
46,60%
N2
19,80%

Site operator

Utility

Gas offtaker

Saint-Florentin (Coved – Paprec)
Operational
fr
WAGABOX® Model
375 scfm
Commissioning
February 2017
Installed capacity
85 304 MMBtu/year
Distance to pipeline
1,9 miles
Landfill gas composition
CH4
45,50%
N2
20,00%

Site operator
Utility
Gas offtaker

Saint-Gaudens (Sivom SGMAM)
Operational
fr
WAGABOX® Model
500 scfm
Commissioning
January 2020
Installed capacity
119,425 MMBtu/year
Distance to pipeline
4.5 miles
Landfill gas composition
CH4
41,80%
N2
27,10%

Site operator

Utility

Gas offtaker
- « Previous
- 1
- 2
- 3
- 4
- Next »